Which logical relationship does the PDM usemost often?

Start to finish
Start to start
Finish to finish
Finish to start

Respuesta :

ExieFansler ExieFansler
  • 25-07-2019

Answer:

Finish to Start.

Explanation:

Finish to Start dependency also known as FS is most commonly used dependency type used between activities in PDM(Precedence Diagramming Method).For example :- in a software you cannot test a screen before it is developed,in construction you cannot paint a building before it is constructed. So we conclude that Finish to start is most commonly used.

Answer Link
phlower11
phlower11 phlower11
  • 10-02-2021

Answer:

Finish to start

Explanation:

I looked it :) hoped it helped

Answer Link

Otras preguntas

What ethnicities contributed to the mosaic of the thirteen colonies?
Under the Articles of Confederation, the principle of "republicanism" helps explain why
use the digits 4 5 and 6 to write a number in which 4 has a value of 400
In a class of 60 students, 5 recieved a grade of A. What fraction of the class did not recieve a grade of A. Reduce in lowest terms
A hill that has a 33.9% grade is one that rises 33.9 m vertically for every 100.0m of distance in the horizontal direction. At what angle is such a hill incline
What steps did women take to win workers’ rights?
-13=7d+64 what is the answer
write 15,409 in two other forms
The revolutionary change of the Neolithic revolution was the shift? of what
is 57 divisible by 4 5 6 9 or 10