Answer:
The conventional B/C ratio is 1.0868.
Explanation:
Here B / C ratio means the benefit by cost ratio, so here we will first individually calculate the benefit and cost which the parks and recreation department will receive.
BENEFIT RECEIVED =
$24,000(people that will come) x 2 (average hour ) x $.50 ( rate per hour )
= $24,000
calculating present value, where i = interest and n = number of years
$24,000 / (1+i)^1 + $24,000 / (1+i)^2 + _ __ _ + $24,000 / (1+i)^20
= $24,000 x [ 1 - 1 / (1+.03)^20 ] / .03 ( given i = 3% )
= $357,060
PRESENT VALUE OF COST INCURRED =
$150,000 + $12,000 / (1+i)^1 + $12,000 / (1+i)^2 + _ _ + $12,000 / (1+i)^20
= $150,000 + $12,000 x [ 1 - 1 / (1+.03)^20 ] / .03
= $328,530
B / C RATIO = $357,060 / $328,530
= 1.0868