Each drill takes $44 in materials and $36 in labor.  So it costs the company ($44+$36)= $80 to MAKE one drill.  THEN they're ready to sell it.  

At the same time, the company has to pay $4,000 just to use the building to make the drills.

I can see at least two different questions here:

Question #1). How much does it cost the company if they MAKE 330 drills in one month ?

Materials and labor:  330 x ($80)  =  $26,400

Rent the building space:  $4,000

Total for the month:  $30,400

Question #2).  How many drills do they have to SELL just to pay back the amount they already spent to manufacture those drills ?

We can't answer that right now, because we don't know the PRICE they charge for each drill when somebody buys it.