Respuesta :
Pump A = 45 mins
Pump B = 35 mins
Pump A and B = (45 x 35) / ( 45 + 35) = 19.69 mins (nearest hundredth)
-
Answer: 19.69 mins
We're looking for the amount of time involved. We know the pumping rates.
First, a look at the units of measurement:
1 job
-----------------------
rate#1 + rate#2 (both in job / time)
When this is simplified, "job" disappears (is cancelled) and time appears in the numerator of the result.
Now, using the actual numbers given:
1 job
-----------------------
1 job 1 job
----------- + ---------------- = 0.0508 job/min
45 min 35 min
Finally, divide "1 job) in the first numerator by this 0.0508 job/min. The result, 19.69, indicates the number of minutes required for both pumps to drain the pool.