In December 2022, Surf Ltd received a claim from one of its customers commencing a lawsuit alleging faults in the construction of a bridge in a housing estate. This lawsuit amounts to a total of $2.5 million in repair costs as at the end of the financial year. As at 20 July 2023 the company's solicitors estimated that about $2 million of the total lawsuit was legitimate and the solicitors believed that there was a high likelihood (i.e. probable) that Surf will need carry out repairs costing $2 million. The remaining $0.5 million of the claim is deemed to be unsubstantiated, thus Surf's solicitors believed that there was a low likelihood (i.e. remote) that the company will need incur these costs. The final court hearing when this lawsuit will be decided is scheduled to 01 August 2023.
Identify the nature of the transaction/event.