Which of the following is not a possible output of the Estimate Costs process?
(Hint: Consult the PMBOK Guide, Sixth Edition, although you should be able to derive the answer from the lectures.)
a. Activity cost estimates
b. Basis of estimates
c. The project's cost baseline
d. Risk register updates

Respuesta :

Otras preguntas

What area did England primarily settle?
The stem plot shows the number of swimming laps completed by swim team members at a single practice. Row 1 has a 5 to the left of the bar and 7, 9 to the right.
calculate the area of regular decogon with a side lenght of 10 cm​
Which features of Word are used to separate numbers and text into columns? Check all that apply. ruler Tab key left tab right tab decimal tab
Define the 13, 14, 15 amendments.
Which of the following is the quality of a good scientific hypothesis?
What’s the value of x in both a & b?
Could -2 be used as a base to rewrite 32? engage" Select one: OYes ONO Submit Answer
trees grow thoughtout the year during witch seasons do you think tress grow faster.
How Spain got along with American Indians​
ACCESS MORE