Octoplez6884 Octoplez6884 30-04-2024 Computers and Technology contestada On the backward pass of a network, if the Late Finish of an activity is 20, and the Duration is 7, what is the Late Start? Use the "new" (the current PMBOK) method of calculation. A. 15 B. 13 C. There are no correct answers. D. 14