Following details regarding cost estimate of a project is given:

Optimistic cost = $ 8,000
Most likely cost = $ 10,000
Pessimistic cost = $ 15,000

Calculate the three-point estimate using triangular distribution.

a) $5,500
b) $10,500
c) $50,500
d) $11,000

Respuesta :

Otras preguntas

find each sum or differences . For the first one
What is the domain and range of the square root function graphed
can u solve this pls
What bearing and airspeed are required for a plane to fly 360 miles due north in 2.0 hours if the wind is blowing from a direction of 331 degrees at 15 mph?
QuestionIn ABC, C = 64°, c = 32, and b = 33. What are the two possible values for angle B to the nearest tenth of a degree?Select both correct answers.
KHG, MZH = 90°, HG = 23, and KG = 31. (Draw picture to help.) What is the value of KH? Answer
Which of the following answer choices is an equation for the circle with a center of (-2, 3) and a radius of 3?
Where are the effects of soil salonization most likely to be seen
Plato please help Which function does this graph represent?
The equilibrium reaction below has the Kc = 4.00. If the volume of the system at equilibrium is decreased from 4.00 liters to 2.00 liters, how and for what reas
ACCESS MORE