The role of the CM changes from Agent for the owner to CM at-Risk when:

1 Upon receipt of an Executed Contract Agreement to perform CM Services
2 The CM assigns risk to contractors performing the work and accepts the responsibility for managing the construction
3 The Construction Phase begins
4 The CM accepts the performance of construction for a fixed price