Reviewing the PERT Network below: If it takes 1, 2, or 3 weeks for each activity (represented by a box) to be completed, the critical path is represented by:
A) Activity A - Activity B - Activity C
B) Activity A - Activity D - Activity F
C) Activity A - Activity E - Activity G
D) Activity A - Activity D - Activity E