Which of the following statements is true of the level of detail for activities?
1) Only one activity per major deliverable is needed for a network plan.
2) Only one activity per project milestone is needed for a network plan.
3) In some cases, it is possible to end up with too much information to manage.
4) It is not necessary to reduce the level of detail as more detail indicates more accuracy.