The role of the CM changes from Agent for the owner to CM at-Risk when:
1 The Construction Phase begins
2 The CM accepts the performance of construction for a fixed price
3 Upon receipt of an Executed Contract Agreement to perform CM Services
4 The CM assigns risk to contractors performing the work and accepts the responsibility for managing the construction