hliles8808 hliles8808 30-01-2024 Law contestada If the contract has a CPI of 0.96 and a SPI of 1.04; what following condition exists?a) Ahead of schedule, over budgetb) Ahead of schedule, under budgetc) Behind schedule, over budgetd) Behind schedule, under budget