Incremental cash flows are estimated to be in order -$2 million, $0.5 million, $4.0 million, and $0.75 million. If the cost of capital is 8%, what is the NPV of this project?

a) $2.49 million
b) -$2.49 million
c) $1.74 million
d) -$1.74 million