You are the project manager on a project that has $1,000,000 software development effort. there are two teams of programmers that will work for seven month for a total of 12,000 hours. according to the project schedule your team should be done with 38% of the work. as of today, the project is 40% complete while 50% budget has been used. calculate and share your conclusion:
a. scheduled variance
b. %of scheduled variance
c. cost variance
d. scheduled of cost variance
e. scheduled performance index (spi)
f. cost performance index (cpi)