The ground fault protection system shall be performance tested when first installed on site. What else is required as part of this performance testing?
1) 230.95(C) requires GFPE to be performance tested when installed using the primary current injection test process.
2) A written record of this test must be available to the authority having jurisdiction.
3) The test shall be conducted in accordance with instructions that are required to be provided with the equipment.
4) All of the above