elladowns9451 elladowns9451 28-12-2023 Engineering contestada A preliminary notice was filed by a contractor 40 days after work started. The period covered by a subsequent lien would start _____A. With the noticeB. 20 days prior to noticeC. 20 days after noticeD. At no time above