The activities summarized in the following table must be preformed by the promoter of a country music concert in Dallas.
Activity Expected Time (in days) Immediate Predecessors
A. Find location 4 -
B. Hire opening act 3 A
C. Hire technicians 3 A
D. Set up radio ads 2 B
E. Distribute tickets 5 B
F. Rent sound and lights 2 B,C
G. Set up newspaper ads 3 B
H. Hire security 1 F
I. Conduct rehearsal 2 Н
What is the critical path for this project?
o A-> B>E
o A->C->E-> F->H->I
o A-> C->F->H-> I
o B>G
o A-> B -> F->H->I