Bahrain Company makes snow blowers. It has two departments that process all products Ambly and Testing. The folurwing data pas to the Ad Direct materials are added at the beginning of the process and conversim easts a uniformly incurred. The degree of completion of conversion of At the beginning of September, work in process is 40% complete and at the end of the month work in process is 60% complete. Odur data for the de

Beginning work-in-process inventory 6,400
Units started 8,000 units
Units completed 12,800 units
Ending work-in-process inventory ?

Conversion costs for September $800,000
Direct materials cost $1,040,000
September Beginning work-in-process costs:
Materials $616,000
Conversion $328,320

Required:
a) Prepare a production cost schedule for the Assembly Department at the end of September using the weighted average method of process costing.
b) Prepare the necessary journal entries.