Question 4


Assume there are five jobs (i. E. , A, B, C, D, and E) that need to be sequenced in a production schedule. The remaining operating time necessary for completion of job A is 3 days (i. E. , job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days, and E will take 8 days. In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?


Question 5


What is the planned-order release using an MRP program if the gross requirement is 5,000 and the inventory on hand is 1,200?