Answer questions 4 to 9 using the following information: The following project network diagram represents Medros & Mariana's project activities for making a new healthy cheesecake. They used the CPM method to solve the project network. They spilled some coffee on the network diagram which caused some numbers to be missing. What are the missing numbers for: Activity [C] (6 Points) 26 0 (6) START - 0 F (20) (3) a. 12 O b. 8 c. 2 B (7) с (2) G (10) FINISH 5 Activity [D] (6 Points) a. 3 b. 8 O c. 5 6 Activity [F] (6 Points) a. 26 b. 28 c. 20 7 The Finish node (6 Points) a. 26 on top & 26 below b. 26 on top & 28 below c. 28 on top & 28 below 8 Activity [E] (6 Points) O a. 5 then 11 O b. 10 then 16 O c. 12 then 18 9 Activity [G] (6 Points) a. 28 b. 26 c. 25