At the end of a week, you measure the progress of task X and find
that it's 25% complete. Now, how do you assess if you are on track to
meet the task budget?
• First, a project manager calculates the planned value for this task (at
the planning stage). Let's say, Task X has a budget of $4000 and is
expected to be 50% complete by the week.