A computer management team has recorded the following data related to average times for production.
Wait Time per order before start of production 15.85 days
Inspection Time per unit, in days 0.45 days
Process Time per unit, in days 0.9 days
Queue Time per unit, in days 3.4 days
Moving Time per unit, in days 1.8 days
Required: Based on the above data, a) Identify the throughput time. b) Determine the manufacturing cycle efficiency. c) Identify the delivery cycle time.