A temporary project costing $135,000 will generate the following annual cash flows over the next three years: $32,000, $64,000 and $78,000. Cleanup will cost $9,000 at the end of year three. Question 23 (2 points) If the cost of capital is 10.0%, what is the NPV of the project?