Resource leveling, or smoothing, levels the resources so that Group of answer choices equal number of resources is assigned to each task. an equal number of tasks are completed each day by the resources on the project. they are applied as uniformly as possible without extending the project schedule beyond the required completion time. the costs for the resources are even as possible across the project.