Rough stuff makes 2 products: khaki shorts and khaki pants for men. each product passes through the cutting machine area, which is the chief constraint during production. khaki shorts take 16 minutes on the cutting machine and have a contribution margin per pair of shorts of $15.0. khaki pants take 20 minutes on the cutting machine and have a contribution margin per pair of pants of $31.5. if it is assumed that rough stuff has 4,600 hours available on the cutting machine to service a minimum demand for each product of 3,000 units, how many pants should be made?