Match the task to the correct phase.

1. creating the communication plan
project-initiation phase
2. completing the project charter
project-planning phase
3. noting the team's accomplishments
project-closure phase
4. monitoring the project schedule
project-execution phase

Respuesta :

Otras preguntas

what does pi mean. full
what is the percent of change in 15 yards to 18 yard
how can one of the multiplication properties help you evaluate (77time25)times 4
Cornerstone Bakery sold 78 pies on Monday, 96 pies on Tuesday, 40 pies on Wednesday, 104 pies on Thursday, and 77 pies on Friday. On average, how many pies did
Which describes the major cause of the French and Indian War? A. disagreements between the French and the Indians over how to use the land and who owns the land
Which statement best describes President Andrew Johnson's overall approach to Reconstruction? He wanted to ensure that there were strong protections for African
Name one reason that parliament raised taxes
Name two decimals that are equivalent to 7.7
25 is 32 percent of what number?
SIMULTANEOUS EQUATION x + 2y = 12 3x - 10y = 0 x = ? y = ? Thanks
ACCESS MORE