Part Two: Using Critical Project Management Tools swer the following questions, using as much space as you need 7 (3) 2 (2) 5 (1) 5 2 3 (2) 2 (3) 4 (2) 2 (3) 6(3) 1 6 3 12 3 (3) 2 (2) 2 (2) 4 10 Duration (#of People) Let's reinterpret the resource demands over time for a left-justified schedule assuming you have five people available. Create a left-justified schedule for the project above, assuming five people, and answer the following questions. 1. Map the earliest start times for each activity to the resource demands over time. What are the earliest start times for each activity? 2. Level the schedule so it is consistent with resource availabilities. What is the new project duration? 3. For this project network, identify the critical sequence. (Frame your answer as Activity Node X to Activity Node Y to Activity Node Z, etc.)