if the irr of normal project x is greater than the irr of mutually exclusive (and also normal) project y, we can conclude that the firm should always select x rather than y if x has npv > 0. if the irr of normal project x is greater than the irr of mutually exclusive (and also normal) project y, we can conclude that the firm should always select x rather than y if x has npv > 0. false true