You are constructing 6 additional rooms on an office building. Each of the 6 rooms is identical, and the projected cost for the project is $100,000 and is expected to take 5 weeks. At the end of the 2nd week, you have spent $17,500 per room and have finished 2 rooms; you are ready to begin on the 3rd. Base on the information provided above; fill in the values for the following table, showing all work (including formulas BAC PV EV AC CV SV CPI SPI EAC ETC VAC TCPI Is the project ahead of or behind schedule Is the project going to be completed over or under budget?