Five batch jobs A to E arrive at the same time. They have estimated running time of 10,2,6,8,4 respectively. Their priority are 3,2,5,4,1 with 5 being the highest priority. For each of the following algorithms, determine mean process turnaround time. Round Robin quantum of 3