2. An industrial engineer wants to implement dynamic task sharing in an assembly cell to meet
increasing demand. The cell currently uses a traditional assembly line balance. In the existing
system tasks a, b, and c are done by worker 1 and tasks d and e are done by worker 2. Tasks
times are shown in the table below. Suggest a scheme for using task sharing to increase
throughput and indicate the expected change in throughput time and production rate. Task time for a is 10, b is 8, c is 8, d is 10, and e is 10.