1. Consider the assembly system shown below. All workstations on the main line have an
average time to failure of 1,000 cycles. Workstations on the feeder lines have an average time to
failure of 800 cycles. All workstations have an average time to repair of ten cycles. The buffer
has a capacity of 10 units. Find the availability of the line.